Categories
Remediation

Over 100 sockeye salmon adults return to spawn in Hazeltine Creek

After seven years of remediation work in Hazeltine Creek in response to the 2014 tailings dam breach, the salmon have returned to the creek to spawn.  In stream work was completed in late August this year, just in time for the sockeye migration in the region.

In the early stages of the Mount Polley remediation effort, 40 thousand truckloads of rock were used to build a foundation channel along Hazeltine Creek from Polley Lake to Quesnel Lake. Next, section by section, the remediation team modified the initial channel and added sinuosity and habitat features to provide instream cover for fish, enhancing the habitat value. These features included spawning platforms, pools, riffles, rock boulder clusters, root wads, and logs.

The biological design for habitat features was developed collaboratively with Mount Polley’s technical experts, Williams Lake First Nation, Xatśūll First Nation, and at the regulatory level, with the Department of Fisheries and Oceans and the Ministry of Forests, Lands and Natural Resource Operations.  Collectively the group is referred to as the “Habitat Remediation Working Group.”

Over the past few weeks over 100 sockeye salmon adults have returned to Hazeltine Creek to spawn. “The focus of the Hazeltine Creek remediation effort at Mount Polley has been to repair and rehabilitate Hazeltine Creek so that it becomes a self-sustaining, productive fish habitat.” said Brian Kynoch, President of Imperial Metals. 

Trout have been using portions of the rehabilitated creek to spawn since 2017, and now another major milestone has been achieved with the return of sockeye salmon to the creek. The presence of the sockeye salmon and various other fish species signals that the remedial work has begun to restore ecological function.  This is not only evident in the aquatic environment but also evident across the terrestrial landscape where plant communities are developing, and abundant wildlife is observed.  It is expected that as both the aquatic and the terrestrial ecosystems mature, further ecological function will emerge, and the site will host an even broader array of organisms.

Categories
Remediation

Fish populations thriving at Mount Polley

Habitat modelling reveals four times more juvenile fish are expected in Hazeltine Creek post-remediation efforts

Mount Polley Mining Corporation is pleased to report that fish populations are thriving at Mount Polley.  Further, the current habitat of upper Hazeltine Creek is over 1.5 times more likely to spawn fish than the pre-breach habitat.  A recent report prepared by Golder, Mount Polley’s Environmental Consultant, reveals that the fish population in Hazeltine Creek is increasing as a result of the remediation efforts made by the Mount Polley Habitat Remediation Working Group* since 2014.  Computer modelling of the fish population projects that there could be up to four times more juvenile trout in Hazeltine Creek in 2031 than in 2014.

“By May 2015 the water in Hazeltine Creek was running clear, and the bugs – invertebrates that provide food for fish – were starting to grow in the creek, so it was decided that the installation of new fish habitat could begin and this work started in 2016,” stated Lee Nikl, Principal and Senior Environmental Scientist – Mine Water and Environment Group at Golder.  “By late 2017, fish were let back into the creek.”

We expect there to be almost twice as many juvenile trout in Hazeltine Creek by 2022.  The new report uncovers that this is an outcome of the remediated habitat features in the creek, as well as the unobstructed conditions for upstream passage of fish, which are expected to persist in the long term.  The Habitat Remediation Working Group has been guiding and overseeing habitat remediation since 2014 and “the design objectives and the designs themselves are the outcome of collaborative design with the Habitat Remediation Working Group”, said Nikl.  “The focus of the remediation effort at Mount Polley has been to repair and rehabilitate Hazeltine Creek so that it becomes a self-sustaining, productive fish habitat.” said Brian Kynoch, President of Imperial Metals.

Categories
Community Exploration Remediation

A letter from the Mount Polley Team

Happy Holidays – we hope that everyone enjoyed a joyous holiday season and wish you all the best for 2021.

A Covid-19 update – Mount Polley employees continue to take additional precautions to minimize the risks of COVID19 transmission and illness as recommended by the Provincial Health Officer. All personnel continued to report to work in Q4.

Employees and site visitors are required to sign off on a daily COVID-19 Questionnaire before entering the site and will be turned away if showing symptoms of illness.

Mount Polley Mine: Care and Maintenance

Bulletins regarding the mines care and maintenance:

  • The environmental monitoring programs continue and are on track
  • Closure research projects continue as planned
  • Remediation of Hazeltine Creek continued at Lower Hazeltine, projected to be complete in 2021
  • Workforce consists of thirteen staff plus additional contractors
  • Site water management continues, including the near-continuous operation of the water treatment plant
  • Exploration Geological Mapping of new areas on mine site
  • CANMAG shipping magnetite

Environmental Monitoring Update

Environmental team: Matt O’Leary, Gabriel Holmes, Kala Ivens, Alicia Lalonde (DWB Consultant), Kim Sandy, Don Parsons (Corporate Office)

New Hire

Kimberly Sandy was hired on November 16 as the newest member of the Mount Polley environmental team.  She has been hired as an Environmental Technician and extensive on-site training is underway.

New ENV Permit

A new ENV permit 11678 was issued on December 31, 2020 that incorporates conditions from a previous consent order because of ongoing appeals of conditions within the permit as issued on February 1, 2020.

Quarter 4 routine monitoring activities completed:

  • Weekly WTP water quality sampling including monthly/quarterly toxicity sampling
  • Monthly water quality sampling at Hazeltine Creek 
  • Monthly & Quarterly water quality sampling of surface & mine affected waters including groundwater, mine seepage
  • Hydrological monitoring
  • Polley Lake, Bootjack Lake, & Quesnel Lake water quality sampling 
  • All critical ditches, sumps, ponds, and pipeline inspections 
  • Monthly/quarterly Waste Inspections
  • Continued investigation of unauthorized discharges and exceedances
  • Reporting—monthly, quarterly, investigations
  • Monitoring planning as per the Comprehensive Environmental Management Plan (CEMP) and ENV Permit 11678

Specialized Environmentally Related Work

During the course of the year, we enlist the help of numerous environmental consulting companies to complete some of the specialized components of the environmental monitoring done at Mount Polley Mine.  Examples include bird song surveys or benthic and invertebrate studies in the remediated areas of Hazeltine Creek.  Most of our consultants completing specialized environmental work have wrapped up their field seasons and are processing data and interpreting their field observations in preparation for delivering their reports.  Some of these reports satisfy CEMP requirements and some are stand alone studies.  The results of this work can be found in the upcoming Mount Polley Mine Annual Environmental Report.  Some of the companies that we engage with include Golder Associates Ltd, Minnow Environmental Inc., DWB Consulting Services Ltd., Ensero Solutions, and Watersmith.

Environmental monitoring is conducted in accordance with the Environmental Management Act (EMA) Permit 11678 and the approved Comprehensive Environmental Monitoring Plan (CEMP) requirements.

Snow corer for evaluating snowpack.

MPMC Water Treatment Plant (WTP) Update

In Quarter 4, the total treated water discharged to Quesnel Lake was ~1,592,581 mᵌ with an average discharge rate of ~0.2mᵌ/second.

The plant operated continuously for most of Quarter 4.  Water quality samples were collected weekly at the Water Treatment Plant (WTP) at the influent (E19) and effluent (HAD-3) sites throughout the quarter.  To further optimize the plant operations the WTP operators have been utilizing a Hanna Multiparameter Photometer to assess influent and effluent copper concentrations to help guide daily plant operations.  We are developing a data set comparing the field readings to the lab results to verify the reliability of the instrument. 

Water Treatment Plant Laboratory

Permit Exceedance

On November 11, 2020, a permit exceedance for elevated copper was observed at the WTP.  Through the course of the resulting investigation, the plant was shut down for four days, additional samples were collected (in recirculation mode), a site contact water review was completed, the source of copper was identified, plant operations and site conditions were assessed key findings were identified and operational recommendations were compiled. The plant resumed normal operation on November 27, 2020.

Bypass Request

On October 26, 2020, MPMC requested a bypass of the authorized works (the WTP) to discharge mine site contact water that is being stored in the Springer Pit without active treatment.  Through the course of the last year, the water quality in the pit has improved greatly and meets the end of pipe permit limits as indicated by the sample results taken during on-site monitoring.  This is the result of the water clarifying and passive in-situ treatment occurring in the pit.  The bypass request also included water from the Tailings Storage Facility (TSF) and the Cariboo Pit provided that they meet the end of pipe permit limits.  Significant water quality fluctuations are not expected because of the single-source nature of the bypass.  Monitoring is planned to increase in the Springer Pit to provide early warning of water quality changes and will remain at the same frequency at the end of the pipe.

Another driver for this request is to aid MPMC in eliminating surplus water currently being stored on site.  The quantity of water stored on-site currently exceeds “Best Practices” as advised by the Tailings Storage Facility Engineer of Record.  A bypass authorization will enable MPMC to increase discharge volumes while still meeting permit limits and BC Water Quality Guidelines. This will also limit year-over-year accumulation of stored water on site.  A similar bypass authorization request was submitted by MPMC in 2016 and approved by the British Columbia Ministry of Environment (MoE) on March 11, 2016.

Water Treatment Plant and Discharge Pipeline to Quesnel Lake

MPMC Water Treatment Plant (WTP) Update-Graph

Hazeltine/Edney Creek Remediation 

Remediation work was limited in Q4 to ground cover seeding and seed collection efforts.  All areas that were disturbed by the 2020 construction near Hazeltine and Edney Creek were seeded.  Additional Sitka Alder and Cattail seeds were collected for distribution.  The native ground cover seed blend that is used in the remediation is comprised of Mountain Brome, Native Red Fescue, Rocky Mountain Fescue, Bluebunch Wheatgrass, Blue Wildrye, Fireweed, and Big Leaf Lupine.

Lower Edney Creek and Secondary High Flow Channel
Newly Constructed Edney Creek Outfall to Quesnel Lake
Hazeltine Creek Reach 3
Ice Forming in Lower Edney Creek

Exploration Update

In late 2019, a comprehensive exploration program consisting of a geochemical MMI-soil sample survey and a geophysical 3D-IP survey was carried out over the Frypan/Morehead area located west and north of the Mount Polley mine. The target area is roughly 3 by 3 kilometers in size, largely till covered and shows a similar magnetic response to that obtained over the Mount Polley mine host rock of monzonite and hydrothermally altered monzonite breccia pipes. 

In June 2020, an additional 3D-IP survey was conducted over the Mount Polley mine site to identify the geophysical response of the known mineralization. 

Interpretation of the new geophysical data sets led to numerous high-priority targets both in the Frypan/Morehead area and on the mine site. 

A drill program was planned to test the new high-priority targets on and off the mine site and to expand zones of known mineralization on the mine site. The first phase of drilling was carried out at the end of 2020. 

Due to prolonged delays with assay labs, the program is waiting for results before drillings resume. 

MPMC EVENTS

Quarter 4, 2020

October 7:

Public Liaison Committee (PLC) Meeting via conference call

Upcoming

February 3, 2020

Public Liaison Committee (PLC) Meeting via conference call

Resources

imperialmetals.com

BC Mine Information Page: https://mines.nrs.gov.bc.ca/

BC Ministry of Environment Natural Resource and Enforcement Database: https://a100.gov.bc.ca/pub/ocers/searchApproved.do?submitType=menu

If you have any questions regarding the Community Update, please email Gabriel Holmes at gabriel.holmes@mountpolley.com

Categories
Monitoring

Mount Polley Environmental Monitoring

Environmental monitoring programs and closure research projects at Mount Polley mine site continue as planned. Remediation construction at the lower Hazeltine Creek and Edney Creek began this summer. Mount Polley staff, with assistance from Golder Associates Ltd., have begun development of the 2022 Water Management Plan.

Monitoring activities include regular water quality and toxicity sampling at:

  • water treatment plant (WTP) 
  • surface waters of Polley Lake, Bootjack Lake, Hazeltine Creek, Edney Creek & Quesnel Lake
  • mine contact waters including groundwater & mine seepage with flow rates

Regular inspections of all critical ditches, sumps, ponds, pumping systems and pipelines.

Ongoing surveys and studies include:

  • spawning activity in Hazeltine & Edney Creeks
  • remediated terrestrial habitats; vegetation growth, nesting sites and wildlife usage
  • aquatic habitats; fish population & tissue, zooplankton, phytoplankton, benthic invertebrates and sediments in Bootjack, Polley & Quesnel Lakes
  • dilution modelling of the Quesnel Lake discharge
  • semi-passive and passive water treatment options for closure which include a constructed wetland treatment system pilot study and a saturated rock fill bench scale test
Tour of aquatic habitat construction in lower Hazeltine Creek
Tour of aquatic habitat construction in lower Hazeltine Creek
Hazeltine Creek Reach One revegetated riparian area – Released under Creative Commons CC0
Categories
Remediation

September site tour with the Habitat Remediation Working Group

The remediation of Hazeltine Creek has been planned and advanced through the direct collaboration of Mount Polley mine employees, government agencies, First Nations and their technical advisors. This collective is called the Habitat Remediation Working Group (HRWG).

Recently, members of Mount Polley mine, Golder Associates Ltd, FLNRO (Ministry of Forests, Lands, Natural Resource Operations and Rural Development) and the Xatśūll First Nation attended a September 2020 HRWG tour.

On the tour the HRWG inspected the construction of habitat features in Lower Hazeltine Creek. The group also inspected the weir and fish ladder at Polley Lake, the functioning spawning habitat in Upper Hazeltine Creek and the terrestrial plant growth in Polley Flats.

The group viewed all stages of remediation, from installation of habitat features to a remediated ecosystem in Upper Hazeltine Creek that is maturing into a self-sustaining landscape used by all manners of life forms.

Discussions on the tour included:
• Local nursery plant sources;
• Local contractors support in the remediation efforts;
• Reflections on how far the remediation has advanced;
• Reopening plans for the mine;
• Plans for the continued use of the weir on Polley Lake for flood control and fish rearing in Hazeltine Creek until the plants in the terrestrial flood plain mature; and
• In stream habitat features installed are potentially superior to those that existed pre-2014.

Below are some photos from the tour (September 2020).

Hazeltine Creek Reach One and revegetated riparian areas looking upstream toward Polley Lake.
Hazeltine Creek Reach One and revegetated riparian areas looking upstream toward Polley Lake.
James Ogilvie, Senior Water Resources Engineer at Golder Associates, describes functionality of reconstructed portions of Hazeltine Creek Reach One
Golder Associates Water Resources Engineer explains functionality of reconstructed portions of Hazeltine Creek Reach One
Hazeltine Creek Reach One and revegetated riparian areas looking downstream
Hazeltine Creek Reach One and revegetated riparian areas looking downstream
Categories
Remediation

Experts recommend leaving tailings in Quesnel Lake

Lately we have received questions about the water quality at Quesnel Lake, so here are a few Q&A’s which address this subject.

First, what it means to conduct remediation?

According to the BC Environmental Management Act, “remediation” means action to eliminate, limit, correct, counteract, mitigate or remove any contaminant or the adverse effects on the environment or human health of any contaminant.

At Mount Polley, using the results of the detailed site investigations, and the human health and ecological risk assessments, the goal of the mine’s environmental remediation work is to repair and rehabilitate the areas impacted by the tailings spill such that they are on a path to self-sustaining ecological processes that result in productive and connected habitats for aquatic and terrestrial species.

As the impacts of the spill were determined to be primarily physical and not chemical, this has meant that the focus of the work has been on repairing and rebuilding habitats. 

Where can I find data about the water quality in Quesnel Lake?

The BC government website hosts an interactive map of surface water monitoring sites in the Province which gives access to results of water sampling and analyses, including Quesnel Lake and other surface water sites around the area of the mine. 

Why was the decision made to leave the tailings at the bottom of Quesnel Lake?

Research and monitoring of the physical and chemical stability of the tailings on the bottom of Quesnel Lake indicate that they are not causing pollution and studies of the bottom-dwelling (benthic) organisms have shown that they are slowly recolonizing the lake bottom as native sediment slowly deposits on top of the organic-poor tailings, bringing organic matter to the lake floor. 

After completing a Net Environmental Benefit (NEB) assessment, experts recommended that the best approach for remediation of the tailings in Quesnel Lake was to leave them alone and cause no further disturbance.

The experts determined that any attempt to remove the tailings could significantly disrupt the present ecosystem and set back the progress that had already occurred.

Remediation at Mount Polley is all about creating the conditions for successful natural recovery, and not doing more damage.

Categories
Remediation

Rainbow trout return to Hazeltine Creek

In 2018 a milestone was celebrated by the Mount Polley Environmental Team (MPET) when the efforts of the remediation work rebuilding Hazeltine Creek witnessed the return of Rainbow Trout, Redside Shiners and Long Nose Suckers to the rebuilt part of the creek.

After the August 2014 tailings spill, fish from Polley Lake were prevented from entering Hazeltine Creek by fish fences above the Polley Lake Weir, while the habitat underwent reconstruction. During the winter of 2014-2015, the creek channel was cleaned up, tailings and debris removed, and a new Hazeltine Creek channel was built and rocked-in.

Fish fences blocking passage from Polley Lake (top left) into upper Hazeltine Creek [2015]
Fish fences blocking passage from Polley Lake (top left) into upper Hazeltine Creek [2015]

In April 2015, the Habitat Remediation Working Group (HRWG*), including the T’exelc First Nation (Williams Lake First Nation) and Xatśūll First Nation (Soda Creek Indian Band) and their consultants, and Mount Polley Mining Corporation (MPMC) representatives and their consultants (Envirowest and Golder), began discussing options for constructing new fish habitat in upper Hazeltine Creek, and requirements MPMC would need to meet in order for fish to be allowed to return to the creek.

*HRWG also includes representatives of the federal Department of Fisheries and Oceans, the provincial Ministry of Environment, and the provincial Ministry of Forest Lands and Natural Resource Operations, both water stewardship and fisheries sections.

Mount Polley employees, consultants, contractors, First Nations and community partners began ecological remediation work on Hazeltine Creek in 2015. By May 2015 the water in Hazeltine was running clear, and the bugs (invertebrates that provide food for fish) were starting to grow in the creek, so it was decided that the installation of new fish habitat could begin and this work started in 2016.

HRWG members looked at historical records to determine what the local conditions were before the spill, and remediation planning was based on that information. The planning was also constrained by the configuration of the constructed rocked-in channel. The group agreed to a field fit approach for the remediation. Conceptual designs were developed by Mount Polley and their consultants, and the plans were reviewed by the HRWG.  

The design approach was to naturalize the rocked-in channel by adding sinuosity (curves and bends), building a sequence of pools, riffles and weirs, and installing boulders, large woody debris and gravel at the bottom of the creek, to provide appropriate spawning and rearing habitat for the fish known to have used upper Hazeltine Creek before the spill, particularly Rainbow Trout, an important species in Polley Lake.

Abundant Rainbow Trout observed upstream of fish fences, looking to transit into Hazeltine Creek from Polley Lake to spawn. [May 2017]
Abundant Rainbow Trout observed upstream of fish fences, looking to transit into Hazeltine Creek from Polley Lake to spawn. [May 2017]

After two years of habitat construction (2016-2017) approximately 2.5 km of spawning and rearing habitat was completed in the upper part of Hazeltine creek from the outlet of Polley Lake to the Gavin Lake Road Bridge. In late 2017, the MPET believed conditions were right to let the fish back into the creek. There was habitat, flowing water, and food, and the water quality met aquatic guidelines.

In December 2017, the HRWG began detailed discussions on the approach to allowing the Rainbow Trout back into Hazeltine Creek. Discussion included requirements for fish monitoring, water quality, sediment quality, habitat quality and quantity, Polley Lake access and egress etc, and the permits and licenses that Mount Polley would have to apply for and comply with from the Ministry of Forests, Lands, Natural Resource Operations and Rural Development Water Stewardship Group.

In March 2018, new fish fences were installed in Hazeltine Creek approximately 2.6 km from the outlet of Polley Lake to prevent fish from going further downstream than the area where habitat reconstruction have been completed. On April 26, 2018, the fish fences at the outlet of Polley Lake to Hazeltine Creek were removed and the Rainbow Trout once again had access to the first 2.6 km of upper Hazeltine Creek.

Note:  the lower part of Hazeltine Creek includes a steep rock canyon that is a natural barrier preventing Quesnel Lake fish from entering middle and upper Hazeltine Creek and Polley Lake. However, in the natural creek system, fish from Polley Lake can be swept down the creek into Quesnel Lake once all the fish habitat reconstruction is completed and fish fences are removed.

In addition to ingress into Hazeltine Creek, the fish also needed to be able to return to Polley Lake. This required that a fishway (ladder) be built for the fish to bypass the Polley Lake Weir water control structure. An engineered fishway was installed by Mount Polley maintenance staff at the Polley Lake weir and the flows are monitored to properly maintain water levels for fish passage.  The fishway was designed so the flow can be adapted to seasonal changes.

Mount Polley fishway ladder
Mount Polley fishway ladder

Fish monitoring was intense in 2018.  MPET worked with Minnow Environmental conducting weekly surveys of the fish populations to track the 2018 spawn and fish activity. The surveys included counting fish at established monitoring stations and pools, and observing how the fish used the creek (i.e. seeking shelter under woody debris or behind boulders). Temperature data and dissolved oxygen levels were also monitored in Hazeltine Creek.

Results of the 2018 Hazeltine Creek fish re-introduction were very impressive. Fish monitors estimated almost 5,000 Rainbow Trout accessed the creek to spawn in spring 2018.  The spawn was successful. A spawning survey in July 2018 observed over 18,600 Rainbow Trout in upper Hazeltine Creek, the majority being from the 2018 spawn.

Spawning rainbow trout in Hazeltine Creek. [late May 2018]
Spawning rainbow trout in Hazeltine Creek. [late May 2018]