Categories
Community Exploration Remediation

A letter from the Mount Polley Team

Happy Holidays – we hope that everyone enjoyed a joyous holiday season and wish you all the best for 2021.

A Covid-19 update – Mount Polley employees continue to take additional precautions to minimize the risks of COVID19 transmission and illness as recommended by the Provincial Health Officer. All personnel continued to report to work in Q4.

Employees and site visitors are required to sign off on a daily COVID-19 Questionnaire before entering the site and will be turned away if showing symptoms of illness.

Mount Polley Mine: Care and Maintenance

Bulletins regarding the mines care and maintenance:

  • The environmental monitoring programs continue and are on track
  • Closure research projects continue as planned
  • Remediation of Hazeltine Creek continued at Lower Hazeltine, projected to be complete in 2021
  • Workforce consists of thirteen staff plus additional contractors
  • Site water management continues, including the near-continuous operation of the water treatment plant
  • Exploration Geological Mapping of new areas on mine site
  • CANMAG shipping magnetite

Environmental Monitoring Update

Environmental team: Matt O’Leary, Gabriel Holmes, Kala Ivens, Alicia Lalonde (DWB Consultant), Kim Sandy, Don Parsons (Corporate Office)

New Hire

Kimberly Sandy was hired on November 16 as the newest member of the Mount Polley environmental team.  She has been hired as an Environmental Technician and extensive on-site training is underway.

New ENV Permit

A new ENV permit 11678 was issued on December 31, 2020 that incorporates conditions from a previous consent order because of ongoing appeals of conditions within the permit as issued on February 1, 2020.

Quarter 4 routine monitoring activities completed:

  • Weekly WTP water quality sampling including monthly/quarterly toxicity sampling
  • Monthly water quality sampling at Hazeltine Creek 
  • Monthly & Quarterly water quality sampling of surface & mine affected waters including groundwater, mine seepage
  • Hydrological monitoring
  • Polley Lake, Bootjack Lake, & Quesnel Lake water quality sampling 
  • All critical ditches, sumps, ponds, and pipeline inspections 
  • Monthly/quarterly Waste Inspections
  • Continued investigation of unauthorized discharges and exceedances
  • Reporting—monthly, quarterly, investigations
  • Monitoring planning as per the Comprehensive Environmental Management Plan (CEMP) and ENV Permit 11678

Specialized Environmentally Related Work

During the course of the year, we enlist the help of numerous environmental consulting companies to complete some of the specialized components of the environmental monitoring done at Mount Polley Mine.  Examples include bird song surveys or benthic and invertebrate studies in the remediated areas of Hazeltine Creek.  Most of our consultants completing specialized environmental work have wrapped up their field seasons and are processing data and interpreting their field observations in preparation for delivering their reports.  Some of these reports satisfy CEMP requirements and some are stand alone studies.  The results of this work can be found in the upcoming Mount Polley Mine Annual Environmental Report.  Some of the companies that we engage with include Golder Associates Ltd, Minnow Environmental Inc., DWB Consulting Services Ltd., Ensero Solutions, and Watersmith.

Environmental monitoring is conducted in accordance with the Environmental Management Act (EMA) Permit 11678 and the approved Comprehensive Environmental Monitoring Plan (CEMP) requirements.

Snow corer for evaluating snowpack.

MPMC Water Treatment Plant (WTP) Update

In Quarter 4, the total treated water discharged to Quesnel Lake was ~1,592,581 mᵌ with an average discharge rate of ~0.2mᵌ/second.

The plant operated continuously for most of Quarter 4.  Water quality samples were collected weekly at the Water Treatment Plant (WTP) at the influent (E19) and effluent (HAD-3) sites throughout the quarter.  To further optimize the plant operations the WTP operators have been utilizing a Hanna Multiparameter Photometer to assess influent and effluent copper concentrations to help guide daily plant operations.  We are developing a data set comparing the field readings to the lab results to verify the reliability of the instrument. 

Water Treatment Plant Laboratory

Permit Exceedance

On November 11, 2020, a permit exceedance for elevated copper was observed at the WTP.  Through the course of the resulting investigation, the plant was shut down for four days, additional samples were collected (in recirculation mode), a site contact water review was completed, the source of copper was identified, plant operations and site conditions were assessed key findings were identified and operational recommendations were compiled. The plant resumed normal operation on November 27, 2020.

Bypass Request

On October 26, 2020, MPMC requested a bypass of the authorized works (the WTP) to discharge mine site contact water that is being stored in the Springer Pit without active treatment.  Through the course of the last year, the water quality in the pit has improved greatly and meets the end of pipe permit limits as indicated by the sample results taken during on-site monitoring.  This is the result of the water clarifying and passive in-situ treatment occurring in the pit.  The bypass request also included water from the Tailings Storage Facility (TSF) and the Cariboo Pit provided that they meet the end of pipe permit limits.  Significant water quality fluctuations are not expected because of the single-source nature of the bypass.  Monitoring is planned to increase in the Springer Pit to provide early warning of water quality changes and will remain at the same frequency at the end of the pipe.

Another driver for this request is to aid MPMC in eliminating surplus water currently being stored on site.  The quantity of water stored on-site currently exceeds “Best Practices” as advised by the Tailings Storage Facility Engineer of Record.  A bypass authorization will enable MPMC to increase discharge volumes while still meeting permit limits and BC Water Quality Guidelines. This will also limit year-over-year accumulation of stored water on site.  A similar bypass authorization request was submitted by MPMC in 2016 and approved by the British Columbia Ministry of Environment (MoE) on March 11, 2016.

Water Treatment Plant and Discharge Pipeline to Quesnel Lake

MPMC Water Treatment Plant (WTP) Update-Graph

Hazeltine/Edney Creek Remediation 

Remediation work was limited in Q4 to ground cover seeding and seed collection efforts.  All areas that were disturbed by the 2020 construction near Hazeltine and Edney Creek were seeded.  Additional Sitka Alder and Cattail seeds were collected for distribution.  The native ground cover seed blend that is used in the remediation is comprised of Mountain Brome, Native Red Fescue, Rocky Mountain Fescue, Bluebunch Wheatgrass, Blue Wildrye, Fireweed, and Big Leaf Lupine.

Lower Edney Creek and Secondary High Flow Channel
Newly Constructed Edney Creek Outfall to Quesnel Lake
Hazeltine Creek Reach 3
Ice Forming in Lower Edney Creek

Exploration Update

In late 2019, a comprehensive exploration program consisting of a geochemical MMI-soil sample survey and a geophysical 3D-IP survey was carried out over the Frypan/Morehead area located west and north of the Mount Polley mine. The target area is roughly 3 by 3 kilometers in size, largely till covered and shows a similar magnetic response to that obtained over the Mount Polley mine host rock of monzonite and hydrothermally altered monzonite breccia pipes. 

In June 2020, an additional 3D-IP survey was conducted over the Mount Polley mine site to identify the geophysical response of the known mineralization. 

Interpretation of the new geophysical data sets led to numerous high-priority targets both in the Frypan/Morehead area and on the mine site. 

A drill program was planned to test the new high-priority targets on and off the mine site and to expand zones of known mineralization on the mine site. The first phase of drilling was carried out at the end of 2020. 

Due to prolonged delays with assay labs, the program is waiting for results before drillings resume. 

MPMC EVENTS

Quarter 4, 2020

October 7:

Public Liaison Committee (PLC) Meeting via conference call

Upcoming

February 3, 2020

Public Liaison Committee (PLC) Meeting via conference call

Resources

imperialmetals.com

BC Mine Information Page: https://mines.nrs.gov.bc.ca/

BC Ministry of Environment Natural Resource and Enforcement Database: https://a100.gov.bc.ca/pub/ocers/searchApproved.do?submitType=menu

If you have any questions regarding the Community Update, please email Gabriel Holmes at gabriel.holmes@mountpolley.com

Categories
Remediation

Mount Polley water quality is evidence of remediation

Mount Polley takes water quality very seriously. Extensive monitoring is evidencing the effectiveness of the remediation and site water management programs undertaken by Mount Polley.

How is water quality monitored in Polley and Quesnel Lakes to ensure proper environmental monitoring is being carried out?

  • Mount Polley follows the BC-ENV approved Comprehensive Environmental Monitoring Plan. The results for all our monitoring sites are published in the publicly available Annual Environmental and Reclamation Reports.
  • You can find a link to the current report here: 2019 Environmental Report 
  • Polley Lake water met all BC Water Quality Guidelines for aquatic life parameters in 2019 with the exception of phosphorus, which was elevated even prior to mining. As Polley Lake is immediately adjacent to the mine site, this indicates the mine is doing a very good job of capturing and controlling run-off.
  • A number of sites are monitored in Quesnel Lake, and in 2019 there were no exceedances of acute BC Water Quality Guidelines.
  • At one monitoring site in Quesnel Lake, there was one minor copper exceedance of chronic BC Water Quality Guidelines in 2019, but as copper is also naturally occurring in the native soils and sediments around Quesnel Lake, and there are a number of creeks that empty into the lake near this sample site, it is difficult to know if this exceedance was natural or related to the mine.

We often get asked if we continue to discharge into Polley Lake or Quesnel Lake?

The mine discharges mine site water, that meets strict permit limits, through diffusers at depth into Quesnel Lake. This water is the only substance the mine is discharging to Quesnel Lake. The mine does not discharge water into Polley Lake.

  • Mount Polley discharges only mine site water that meets strict Environmental Management Act (EMA) permit guidelines.
  • treated by a water treatment plant, when needed to meet permit requirements, before being released into Quesnel Lake. The water going into the treatment plant (influent) is monitored on an ongoing basis, and the treated water leaving the plant (effluent) is sampled regularly for analysis. Not all water at Mount Polley requires treatment to meet EMA permit water quality guidelines before discharge, and in the past, water that was simply stored in Springer Pit was found suitable for passive discharge.
  • The lake water quality is also routinely monitored and sampled regularly as part of the mine’s Comprehensive Environmental Monitoring Plan.

Continued monitoring data confirm that remediation efforts are effective.

  • Currently, there are no indications in the monitoring data that the water discharged from Mount Polley is having any negative effects on Quesnel Lake water quality or aquatic life.
  • If you are interested in looking at water quality data collected on surface water in the area around the Mount Polley mine, in addition to data in the mine’s annual reports, results are available through the BC Government Surface Water Monitoring Sites Interactive Map.

Categories
Mining facts

Is Mount Polley Dumping Waste into Quesnel Lake?

There has been recent speculation about whether or not Mount Polley is dumping waste into Quesnel Lake. In short, the answer is no. Current treatment of water at Mount Polley, including the dilution zone at depth in Quesnel Lake, ensures water released into Quesnel Lake is in line with BC and Canadian water quality standards. Mount Polley discharges only treated mine site water that meets strict Environmental Management Act (EMA) permit guidelines.

All mine site water is collected and is treated by a Veolia ACTIFLO™ water treatment plant before it is released into Quesnel Lake. (see veoliawatertech.com for more information on their treatment systems and how they work.) The water going into the WTP (influent) is monitored on an ongoing basis (measurements of turbidity every 15 seconds) and the treated water leaving the plant (effluent) is sampled regularly for analysis. The lake water quality is also routinely monitored and sampled regularly as part of the mine’s Comprehensive Environmental Monitoring Plan.

The following are facts that explore, in more detail, the discharge from Mount Polley into Quesnel Lake. We hope this information provides factual clarity about Mount Polley’s approved activities.

Is Mount Polley’s discharge having negative effects on Quesnel Lake?

There are no indications in the monitoring data that the Mount Polley discharge is having any negative effects on Quesnel Lake water quality. If you are interested in looking at some of the water quality data that has been collected on surface water in the area around the Mount Polley Mine, the results are available through the BC Government Surface Water Monitoring Sites Interactive Map

Is the water in Quesnel Lake contaminated? Is it safe to drink?

At this time, there are no indications of contamination of Quesnel Lake water from the Mount Polley spill. The mine, and the Ministry of Environment and Environment Canada, continue to monitor Quesnel Lake. With the exception of natural causes, the lake does not exceed environmental guidelines for any of the constituents of concern that are found in the Mount Polley tailings.

As early as August 12, 2014, BC’s Interior Health Authority (IHA) rescinded all water use restrictions from Quesnel Lake (including for “drinking water, personal use, fishing, swimming and recreational purposes”), except for the immediate impact zone where Hazeltine Creek entered Quesnel Lake. The IHA notice also stated that “Interior Health has no reason to believe that this water was ever exposed to unsafe levels of contaminants from the mine breach. As a result, flushing and testing of individual water supply systems is not considered necessary.”

All water use restrictions were fully rescinded July 13, 2015. (Note: IHA always advises that surface water be treated for pathogens prior to use/consumption.)

How much is the mine discharging into Quesnel Lake?

The Environmental Management Act permit annual average authorized discharge rate is 29,000 cubic meters per day. The actual discharge rate depends upon the rainfall experienced at site which varies from year to year. In 2019, the annual average discharge rate has been 14,883 cubic meters per day, significantly less than the mine’s permit allows.