Mount Polley Remediation’s 2019 Environmental Update

Extensive remediation work in the areas affected by the 2014 breach at Mount Polley has been achieved during the past five years.

Over $70 million dollars has been spent on clean-up work, including environmental impact and risk assessment studies, and remediation and monitoring of areas impacted by the spill.

Throughout 2019, the environmental department collected 1,115 water and soil samples. 336 surface water, 234 lake samples, 104 contact water, 77 groundwater, 181 seep, and 153 soil/other samples.

The construction on Hazeltine Creek concluded at the beginning of October and will re-commence at Lower Hazeltine in the Spring of 2020. The flow of Hazeltine Creek was monitored monthly.

There are 3 on-site environmental technicians to do the water sampling, environmental monitoring, inspections including reporting, database, spreadsheet data entry, communication, and coordinating meetings/tours.

Even though environmental monitoring slows down in the winter months, the environmental staff remain busy in the office with reporting, data entry, database management, scheduling, meetings, shoveling snow and general cleaning duties.

We continue to work hard to exemplify the highest site remediation standards and look forward to updating you as our work continues.

Share This Article

Subscribe to our Newsletter